57Case studies

  • Muddy_Creek
    United StatesNorth America

    Muddy Creek Wastewater Treatment Plant (USA)

    COMBINED HEAT AND POWER FACILITY
    helps wastewater treatment plant increase efficiency, reduce power costs, meet environmental compliance

    Location

    Winston-Salem, North Carolina, USA

    Installed engine

    1 x J416

    Electrical output

    1,137 kW

    Thermal output

    805 kW

    Energy source

    Sewage gas

    Commissioned

    2020

    Muddy Creek Wastewater Treatment Plant (USA)
  • Stadtwerke Bad Säckingen interior
    GermanyEEA and Switzerland

    Stadtwerke Bad Säckingen (GER)

    NEW GENERATION
    Jenbacher J420 E driving the energy transformation forward

    Location

    Säckingen, Germany

    Installed engines

    1 x J312, 2 x J416, 2 x J420 E

    Electrical output

     5.7 MW

    Thermal output

     6.2 MW

    Energy source

    Biomethane

    Commissioned

    2012, expanded: 2020

    Stadtwerke Bad Säckingen (GER)
  • BGA Hogl Biogas​
    GermanyEEA and Switzerland

    BGA Högl - Biogas​ (GER)

    BGA Högl

    Location

    Volkenschwand, Germany

    Installed engines

    2 x J420 D25

    Electrical output

    1,501 kW​

    Energy source

    Biogas

    Commissioned

    2018

    BGA Högl - Biogas​ (GER)
  • Haag Preis interior
    GermanyEEA and Switzerland

    Bioenergie Haag-Preis​ (GER)

    Bioenergie Haag-Preis​

    Location

    Rain, Germany

    Installed engine

     1 x J420 D25​

    Power output

    1,500 kW

    Energy source

    Biogas

    Commissioned

    2018

    Bioenergie Haag-Preis​ (GER)
  • WR Aerial
    United StatesNorth America

    Wolf Run, IMG Energy Solutions (USA)

    MEETING INDEPENDENT POWER PRODUCER'S PEAK POWER NEEDS
    A highly flexible, quick start, modular 5-unit solution is delivering 21 MW of reliable power

    Location

    Bradford County, Pennsylvania, USA

    Installed engines

    5 x J624

    Electrical output

     21.8 MW

    Electrical efficiency

    44.7%

    Energy source

    Pipeline gas

    Commissioned

    2019

    Wolf Run, IMG Energy Solutions (USA)
  • SkyGlobalProject1
    United StatesNorth America

    Sky Global Power One (USA)

    Natural gas power plant provides grid support during unusual winter storm crisis in Texas

    Location

    Rock Island, Texas, USA

    Installed engines

    6 x J920 FleXtra 

    Electrical output

    51 MW

    Energy source

    Pipeline gas

    Commissioned

    2016

    Sky Global Power One (USA)
  • Owensboro 1
    United StatesNorth America

    Owensboro Grain Company (USA)

    Combined heat and power facility helps grain processing company significantly reduce its dependence on utility power, slash power costs.

    Location

    Owensboro, USA

    Installed engines

    3 x J620 

    Electrical output

    9.9 MW

    Energy source

     Pipeline gas

    Commissioned

    2014

    Owensboro Grain Company (USA)
  • MCAS Image 1
    United StatesNorth America

    U.S. Marine Corps Air Station (USA)

    Cogeneration means reliable power, cost savings for the U.S. Marine Corps

    Location

    Beaufort, South Carolina, USA

    Installed engine

    1 x J320 

    Electrical output

    1 MW

    Energy source

    Pipeline gas

    Commissioned

    2010

    U.S. Marine Corps Air Station (USA)
  • Stadtwerke Rosenheim
    GermanyEEA and Switzerland

    Stadtwerke Rosenheim (GER)

    The J920 FleXtra engine from INNIO allows the city of Rosenheim to generate flexible distributed power & heat by operating in a highly efficient combined heat and power application mode.

    Location

    Rosenheim, Germany

    Installed engine

     1 x J920 FleXtra

    Electrical output

     9.5 MW

    Thermal output

     10 MW

    Energy source

    Pipeline gas

    Commissioned

    2017

    Stadtwerke Rosenheim (GER)

The Chatbot that we use at our website uses cookies categorized as "Chatbot Cookies". If you click on "START CONVERSATION", you will accept usage of cookies from the category "Chatbot Cookies" and start using the Chatbot. If you want to learn about cookies that we use on our website, please visit the Privacy Preferences Center.